Q3 2021 Engineering Update

source on github

Q3 2021 PM Progress

  • Roadmap update: scheduled, to be updated Sept 18th, 2021

August/September 2021

For period starting August 14, ending Sept 15th

view charts and graphs for select project analytics

30 Day Progress Report

10 Epics had Stories completed
0 Epics were finished

  • Integrate an external arb engine increased from 0% to 100% complete, expanded from 0 to 5 Stories, and 5 Stories were finished.
  • Documentation Internal and External increased from 0% to 100% complete, and 3 Stories were finished.
  • Sushi Specification increased from 0% to 100% complete, 1 Story was finished, and was marked as Done.
  • GTM/Market increased from 12% to 100% complete, and 7 Stories were finished.
  • End to End v1 Production increased from 72% to 75% complete, expanded from 11 to 12 Stories, and 1 Story was finished.
  • Smart Contract optimizations / bugfixes increased from 60% to 70% complete, and 1 Story was finished.
  • CI/CD Omnibus increased from 44% to 66% complete, and 2 Stories were finished.
  • Deploy Ethereum Clients increased from 0% to 66% complete, and 2 Stories were finished.
  • SushiSwap Production Integration increased from 20% to 64% complete, expanded from 10 to 14 Stories, and 7 Stories were finished.
  • KDB Improvements increased from 0% to 62% complete, expanded from 0 to 24 Stories, and 15 Stories were finished.

Roadmap Tracking

If you would like to see something added either on the roadmap or on the updates, please comment and let us know.

2 Likes

apologies for the quality of the images. Clubhouse.io recently changed their name to shortcut.com and their export images functionality is broken for reports, so JPEG’s it is. :frowning:

Nice update, congratulations team!

1 Like

It is great if I can see the stories. (even only titles.)

Working incredibly hard! :trophy:

1 Like